This procedure sets forth guidelines to assist state-operated campuses of the State University of New York (University) in the procurement of materials, supplies, equipment, construction, construction-related services and services from New York State certified minority- or women-owned business enterprises (MWBE). Specifically, it outlines steps that campuses must employ in the procurement process for commodities and services (Procedure Item 7553) and construction (Procedure Item 7554) and construction-related services (Procedure Item 7555) in order to be in compliance with Federal Equal Employment Opportunity Act of 1972 (P.L. 92-261), NYS Executive Law Article 15-A, 5 NYCRR Part 140 and University MWBE policy (Procedure Item 7556).
This procedure applies to all procurements exceeding $25,000 for labor, services (including architectural and design services), supplies, equipment or materials, and for procurements exceeding $100,000 for the acquisition, construction, demolition, replacement, major repair or renovation of real property and improvements.
System-wide:
The State University of New York's System-wide MWBE Program will comply with NY Executive Law Article 15-A, 5 NYCRR Part 140, Federal Equal Employment Opportunity Act of 1972 (P.L. 92-261), University MWBE policy (Procedure Item 7556), and the SUNY Board Resolution January 2012 entitled “Minority and Women Enterprises Utilization Reports.” The responsibilities include, but are not limited to the following:
Appointment and Responsibility of Campus MWBE Coordinator:
Each campus shall appoint an MWBE Program Coordinator or designee who shall be responsible for the campus compliance with the MWBE Program.
Responsibilities:
The MWBE Program Coordinator or designee is responsible for full implementation of Procedure 7557 and monitoring for compliance on contracts.
-
OBJECTIVES
It is the policy of the University to ensure that MWBEs, as defined in Article 15-A, have an equal opportunity to receive and participate in University procurements. Through the implementation of this procedure, the University intends to:
-
permit only firms certified by Empire State Development (ESD) to participate on SUNY contracts as MWBEs;
-
create a level playing field on which MWBEs can compete fairly for University procurements;
-
ensure nondiscrimination in the award and administration of contracts;
-
assist to eradicate artificial barriers to the participation of MWBEs in State contracts.
-
OVERSIGHT RESPONSIBILITIES
-
Submit to Empire State Development (ESD):
-
an annual Master Goal Plan; and
-
a quarterly compliance report including, but not limited to, the number of total SUNY contracts awarded, the maximum dollar amount obligated to those contracts, and total expenditures pursuant to all such contracts; same for contracts awarded to certified MBE or WBE.
-
Provide:
-
an annual report to the SUNY Board of Trustees that compares established MWBE goals with the University's actual MWBE participation;
-
a performance evaluation for campus presidents addressing their respective campus compliance with the University MWBE program;
-
an annual Goals Bulletin that provides separate goals, broken down by contract type, for participation of certified minority- and women-owned business enterprises (MWBEs) and equal employment opportunity (EEO) participation on all SUNY contracts;
-
assistance to campuses with goal assignment on campus contracts
-
goals setting training, goal preparation tools;
-
review and approve goals and utilization plans which fall below established System-wide goals threshold as published in the annual Goals Bulletin;
-
a partial or total waiver of goal requirements established on a contract provided there is documentation of good faith efforts by the vendor/contractor to meet the goal requirements of the contract.
-
Training for campuses' designated MWBE Program Coordinator(s) on MWBE requirements and providing updates on regulations.
-
In consultation with the Assistant Vice Chancellor for Procurement, review campuses' compliance with MWBE procedures as necessary.
-
Appointment: The MWBE Program Coordinator or designee who shall be identified by the campus President, or designee on the MWBE Program Coordinator Designation (Form 7557-122) and forwarded to the System-wide MWBE Program Office.
-
In order to ensure continuity of operation and training on Procedure 7557, the MWBE Program Coordinator shall notify the System-wide MWBE Program Office prior to vacating this responsibility. The campus President or designee is responsible for notifying the System-wide MWBE Program Office of a replacement.
-
MWBE REQUIREMENTS - DEMONSTRATING A GOOD FAITH EFFORTS
NYS Executive Law Article 15-A and University policy require campuses, as well as the vendors and contractors with whom they do business, to make a good faith effort to procure materials, supplies, equipment and services from NYS certified MWBEs and to meet University-established goals for MWBE participation in a State contract.
The University is required to submit an annual plan establishing MWBE goals to Empire State Development (ESD). The University's agency specific goals pursuant to NYS Executive Law Article 15-A, Section 313 (1) (“Section 313 Goals”) are published in accordance with required disparity studies conducted by ESD. These goals may be applied on the entire project for the State fiscal year following the publication of the corresponding disparity study. Contract specific goals may also be assigned through the MWBE Goal Setting process.
The University is required to document a good faith effort in procurements by employing the actions outlined in sections below.
-
PRE-SOLICITATION PHASE
The primary activity in the pre-solicitation phase is to assign goals that consider certified MWBE firms identified as either a prime or subcontractor on contracts the campuses intend to let.
MWBE goals are defined as the percentage of aggregate agency expenditures targeted for the participation of certified minority- and/or women-owned business enterprises sought to be included in State procurement opportunities as prime contractors, subcontractors, suppliers, consultants, joint ventures, teaming agreements, or other similar arrangements. Goals may be expressed as annual Statewide (also referred to as “Section 313 goals”), agency-specific or contract goals.
-
Goal-Setting Methodology
The MWBE Goal Setting Primer is provided to assist campus MWBE Program Coordinators in the day-to-day administration of SUNY's contract-specific goal setting process.
When calculating contract-specific goals the MWBE Program Coordinator or designee will:
-
Determine whether goals are feasible in the participation of certified MWBEs in the procurement opportunity.
-
Determine if procurement is exempt, excluded, or a term agreement.
-
Determine whether the campus can utilize SFL §163.6 to make discretionary purchases to increase the probability of soliciting quotes from NYS certified MWBEs on that procurement.
-
Conduct a vendor and spend analysis within the New York State Contract System (NYSCS) Goal Setting module to determine whether there are NYS certified MWBEs that are available to participate in the procurement.
-
Determine whether, based upon the commodity codes relevant to the procurement, there are NYS certified MWBEs, both inside and outside of the campuses' region, that have indicated their availability:
-
in the ESD MWBE certification database; or
-
in response to a campus' inquiry.
-
Prepare a list of potential MWBE's that have indicated in the ESD MWBE certification database an interest in the procurement for outreach.
-
Determine if components of the project can be separately procured or the project can be progressed using a phased contract approach in order to increase participation without compromising project delivery. This approach is referred to as unbundling.
-
Prior to advertising in the NYS Contract Reporter, the MWBE Program Coordinator will provide the MWBE goals to the contract administrator for insertion into the NYS Contract Reporter, Exhibit A-1 and other solicitation documentation.
-
Factors to Consider when Establishing Contract Goals
-
MWBE Program Coordinator shall establish goals for participation of certified MWBEs on all State contracts, where applicable. University campuses must notify Contractors in bid documents, requests for proposals, contract announcements or advertisements or otherwise in writing of the goals established on State contracts. University campuses shall provide an electronic link to the NYS or official current list of certified minority- and women-owned business enterprises to each prospective contractor. In determining what goals are appropriate in relation to a particular State contract, the MWBE Program Coordinator must give consideration to the following factors:
-
the contract and subcontract scope of work;
-
the number and type of certified MWBEs available in the State or official directory to perform the State contract work, and their availability in the region of contract performance;
-
the total dollar value of the work required by the State contracts, in relation to the dollar value of subcontracts of the contract scope of work;
-
the relationship of the size and term of a State contract to the size and term of a project for which purpose the State contract is awarded;
-
the percentage of certified MWBEs located outside the region, and their availability in the region of contract performance;
-
the potential subcontract opportunities available in a contract and the availability of certified MWBEs to respond to the potential subcontract opportunities;
-
Past performance of MWBE utilization absent the effects of past and current discrimination on contracts of similar scope;
-
A Pre-Solicitation Waiver (7557-14b) must be submitted to the System-wide MWBE Program prior to advertising when teh goals that are set below the established agency goal threshold in the annual MWBE Guidance Bulletin;
-
Documentation to accompany the formal pre-solicitation waiver request is: (1) Completed Goal Setting documentation from the NYSCS Goal Setting module; and (2) documentation of good faith efforts undertaken at the campus level to ascertain MWBE availability;
-
In consultation with the campus, the System-wide MWBE Program will determine whether additional action needs to be taken to meet established goals or whether a formal request will be made to assign lower goals.
-
If a State contract is entered into on an emergency basis or where an amendment or change order has been added to a State contract providing for a total expenditure in excess of $25,000, University campuses may require the contractor to submit a utilization plan and to comply with other post award requirements during the life of the contract.
-
Diversity Practices
The University shall determine whether it is practical, feasible and appropriate to include in the evaluation of bids or proposals the diversity practices of all contractors making submission for the award of any State contract that is:
The MWBE Program Coordinator will score the Diversity Practice Questionnaire, which can be found in the Request for Proposal boilerplate, using the Diversity Practices Scoring Rubric (Form 7557-125). This final score will be calculated on the NYS Diversity Practices Scoring Matrix (Form 7557-126). Diversity Practices will be a weighted score up to 10% of the technical.
-
Awarded on the basis of best value, or otherwise awarded as a response to a request for a proposal and/or a request for qualification; and
-
Anticipated to result in an award of two hundred fifty thousand dollars ($250,000) or greater; and
-
Not a contract based on lowest price.
-
SOLICITATION PHASE
-
The campus will incorporate the goals agreed upon into the Exhibit A-1 and incorporate the said Exhibit A-1 into the solicitation along with any other information that the MWBE Program Coordinator deems relevant.
-
In addition to identifying a designated contact for procurement related activities, the campus will identify a designated contact for MWBE-related inquiries. The statement below should be inserted in all procurement solicitations:
-
“For inquiries related specifically to Minority Women-Owned Business Enterprises (MWBE) provisions of this procurement solicitation, the designated contact is: list name, title, address, telephone number and email address.”
-
The MWBE contact will respond to questions and requests for clarification received by telephone or visitation by bidders or their representatives.
-
All submission should cite the specific MWBE section in the solicitation prompting the inquiry.
-
Pre-proposal/Pre-bid Conference or walk through: If the campus holds a Pre-proposal/Pre-bid conference as specified in the solicitation, an opportunity to clarify MWBE related questions and for MWBE firms to meet other prospective bidder's firms must be facilitated.
-
The campus contract administrator shall include as a topic of discussion (in any pre-bid, walk through and/or pre-proposal meetings) MWBE goals and participation requirement.
-
The MWBE Pre-Proposal/Pre-Bid Information Script is available on Form 7557-123_Pre-bid Information Script.
-
The MWBE Program coordinator will discuss with prospective bidders SUNY's MWBE policy and requirements necessary to submit an acceptable utilization plan and good faith efforts documentation.
-
The campus contract administrator will issue a public notice of the procurement opportunity through advertisements and outreach as follows:
-
Procurements above $50,000 require that an advertisement be placed in the New York State Contract Reporter.
-
A notice of solicitation (i.e., by phone, letter or preferably email) should be sent to:
-
The NYS certified MWBE vendors, as developed through the goal setting process. Note: A disclaimer may be included to state that the MWBE vendor list is not prequalified by the campus.
-
1. The full directory of NYS certified MWBE vendors is produced by ESD and is available on-line at https://ny.newnycontracts.com/
-
All advertisements and notices should be sent in a timely fashion allowing MWBEs at least 15 days notification in advance of the response date if the procurement is greater than $50,000.
-
If campuses develop a selective bidders list, campuses must include MWBEs on this selective list to prospective bidders as identified during the goal setting process pursuant to 5 NYCRR Part §141.6(b) (6)).
-
SELECTION AND AWARD PHASE
-
The following MWBE documentation is required with submittal of the bid or proposal:
-
Commodities and Services - The MWBE Program Coordinator will review the forms listed below to ensure the integrity of the MWBE information being submitted. The Campus procurement evaluation committee approves all sub consultants for services. The MWBE Program Coordinator approves whether the MWBE component is meaningful and acceptable. This is done in collaboration with campus selection professionals. The MWBE component is vetted prior to selection and then again after selection with the submission and review of the following forms:
-
MWBE Utilization Plan Worksheet (7557-107)
-
MWBE-EEO Staffing Plan (7557-108)
-
Vendor/Contractor EEO Policy (7557-104)
-
MWBE Service/Consultant GFE Rating (7557-119)
-
Construction-Related Consultants Services - The MWBE Program Coordinator will review to ensure the integrity of the MWBE information being submitted (i.e. MWBE certification status, approved commodity codes, etc.). The campus procurement evaluation committee approves all sub consultants. The MWBE Program Coordinator approves whether the MWBE component is meaningful and acceptable. This is done in collaboration with campus design professionals. The MWBE component is vetted prior to selection and then again after selection.
The following MWBE documentation is required within seven days of submittal of the bid or proposal:
Note: Campuses have the option to make this request more restrictive and elect to require the utilization plan submitted with the bid if they choose.
-
Receipt of the Sub-consultant/MWBE Staffing List
-
Architecture/Engineering Design Sub-Consultant/MWBE Staffing List (7555-15)
-
Construction Management Sub-Consultant/MWBE Staffing List (7555-16)
-
Commissioning Services Sub-Consultant/MWBE Staffing List (7555-17)
-
Contractor EEO Policy Statement (7557-104)
-
Construction
-
Receipt of the MWBE utilization plan and staffing plan is required within seven days of submittal of the bid. These documents, as noted below, shall be submitted by the three apparent low bidders to the campus MWBE Program Coordinator who will review them with campus design professionals.
-
MWBE Utilization Plan Worksheet (7557-107)
-
EEO Staffing Plan (75575-108)
-
Vendor/Contractor EEO Policy or SUNY Form (7557-104)
-
Additional MWBE forms and documentation will be required if the Utilization Plan is determined deficient.
-
MWBE-EEO Work Plan (Form 7557-105)
-
Contract Breakdown (Form 7557-106)
-
MWBE Rating Forms shall be used by the MWBE Program Coordinator for service/consultant, construction consultant and construction contracts.
-
Construction Consultant Selection Rating (7555-06)
-
Backdrop Term Consultant Mini Selection (7555-07)
-
Evaluation of Design Firm Response (7557-124)
-
Diversity Practices Scoring Rubric (7557-125)
-
NYS Diversity Practices Scoring Matrix (7557-126)
-
MWBE DOCUMENTATION REVIEW AND APPROVAL
-
At the direction of the MWBE Program Coordinator, the prime susceptible to award will enter utilization plan information directly online into the NYSCS Statewide Utilization Management Plan (SUMP) module.
-
Should the prime susceptible to award require assistance in accordance with the Americans with Disabilities Act, or experience technical difficulties, contact technical support at https://ny.newnycontracts.com/FrontEnd/ContactForm.asp?TN=ny&XID=2388
-
Prior to the contract being signed, the MWBE Program Coordinator in consultation with appropriate campus staff must review and approve all MWBE documentation (i.e. Staffing Plan, Utilization Plan, etc.) for construction, construction consultant, services and commodity contracts within twenty (20) business days, as required by 5 NYCRR §142.4.
-
A utilization plan will only be approved by the campus MWBE Program Coordinator when it meets or exceeds the approved advertised goals.
-
If the utilization plan submitted is deficient, the MWBE Program Coordinator will provide the contractor with a written notice of deficiency (email) of the Utilization Plan within twenty (20) business days of its receipt, as required under 5 NYCRR Part 142.6(c). Should a notice of deficiency be issued, it shall include but not be limited to the following:
-
A list of NYS certified MWBEs that the contractor could potentially use as a subcontractor;
-
Any other information which the MWBE Program Coordinator determines to be relevant to developing an approvable MWBE Utilization Plan.
-
In addition to a revised Utilization Plan, the MWBE Program Coordinator may require additional MWBE documentation if awardees submit deficient MWBE good faith effort documentation. These documents are as follow:
-
7557-101: MWBE Contractor Solicitation Letter
-
7557-102: MWBE Participation Quote
-
7557-103: MWBE Contractor Unavailability Certification
-
7557-106: Contract Breakdown and Sample.
-
The contractor shall respond to the notice of deficiency by submitting to the MWBE Program Coordinator a written remedy within seven (7) business days, as required by 5 NYCRR Part 142.6(e).
-
If the deficiency is rectified and the revised utilization plan meets or exceeds approved advertised goals, the MWBE Program Coordinator will approve the utilization plan.
-
If the deficiency is not rectified, and the contractor is requesting a waiver:
-
The MWBE Program Coordinator will notify the contractor and direct the same to submit, within five (5) business days, a request for partial or total waiver of MWBE-EEO goals as required by 5 NYCRR Part 142.6 (f) on Form 7557-114 provided by the University-wide MWBE Program Office.
-
List of the general circulation, trade and MWBE-oriented publications and dates of publications soliciting for certified MWBE participation as a subcontractor/supplier and copies of such solicitation.
-
List of the certified MWBEs appearing in the Empire State Development MWBE directory, https://ny.newnycontracts.com ,that were solicited for this contract. Provide proof of dates or copies of the solicitations and copies of the responses made by the certified MWBEs. Describe specific reasons that responding certified MWBEs were not selected.
-
Descriptions of the contract documents/plans/specifications made available to certified MWBEs by the contractor when soliciting their participation and steps taken to structure the scope of work for the purpose of subcontracting with or obtaining supplies from certified MWBEs.
-
Description of the negotiations between the contractor and certified MWBEs for the purposes of complying with the MWBE goals of this contract.
-
Other information deemed relevant to the request.
-
The MWBE Program Coordinator is to submit to the System-wide MWBE Program a pdf copy of the deficient Utilization Plan entered into the SUMP module of the NYSCS, along with the Vendor's/Contractor's good faith documentation, Form 7557-114 Prime MWBE Post Solicitation Waiver Request and 7557-114a Campus MWBE Post Solicitation Waiver Request Form.
-
The System-wide MWBE Program, in consultation with the MWBE Program Coordinator, will determine whether additional action can be taken to assist the vendor/contractor reach their goal or whether a formal request will be made to the Chief Diversity Officer in the Governor's Office to waive the goal partially or in full.
-
In addition to a revised Utilization Plan, the MWBE Program Coordinator may require additional MWBE documentation if the prime susceptible to award submits deficient MWBE good faith effort documentation.
These documents are as follow:
-
7557-101: MWBE Contractor Solicitation Letter
-
7557-102: MWBE Participation Quote
-
7557-103: MWBE Contractor Unavailability Certification
-
7557-106: Contract Breakdown and Sample.
-
If a contractor is deemed non-responsive or non-responsible by the System-wide MWBE Program, the request for a waiver shall be deemed to be moot (5 NYCRR Part 142.7(a) (1) (b)).
-
The System-wide MWBE Program, in consultation with the Chief Diversity Officer in the Governor's Office, may grant a partial or total waiver of goal requirements established on the contract only upon the submission of information supporting a waiver request by the vendor/contractor and the verification of requisite documentation of good faith efforts by the vendor/contractor to justify a waiver request.
-
Should the waiver request be denied by the System-wide MWBE Program, this may be grounds for disqualification of the Contractor's bid or proposal.
-
Failure to file the waiver form in a timely manner may be grounds for disqualification of the Contractor's bid or proposal.
-
Business Officer or campus designee, upon consultation with SUNY Counsel, the System-wide MWBE Program and the MWBE Program Coordinator, may disqualify (5 NYCRR §142.6(f)) a contractor as being non-responsive to the requirements of NYS Executive Law Article 15-A if the contractor:
-
Fails to submit a MWBE Utilization Plan;
-
Fails to submit a written remedy to a notice of deficiency to a MWBE Utilization Plan;
-
Fails to submit a request for waiver;
-
Receipt of a waiver request denial from the University-wide MWBE Program Office; or
-
Determines that the vendor/contractor/consultant has failed to perform good faith efforts.
-
The campus contract administrator will ensure that the Exhibit A-1 with the contract specific goals is included in the contract.
-
Workforce Employment Utilization Report (“Workforce Report”)
-
The Contractor shall submit a Workforce Report, and shall require each of its Subcontractors to submit a Workforce Report directly online by logging into the New York State Contract System (NYSCS) https://ny.newnycontracts.com/ and responding to Workforce Audit Reminders, and to require any of their subcontractors on the contract to do the same, on a monthly basis for construction contracts, and a quarterly basis for all other contracts, during the term of the contract.
-
Workforce Reports shall be reported on a monthly basis for construction contracts and a quarterly basis for all other contracts.
-
Separate forms shall be completed by the Contractor and the Subcontractor.
-
The MWBE Program Coordinator will direct the prime contractors to submit directly online in the NYSCS in the timeframes prescribed above.
-
Within (10) business days of contract award, the MWBE Program Coordinator will ensure that the approved utilization plan information has been entered into the NYSCS.
-
The MWBE Program Coordinator may be required to provide the campus with copies of signed MWBE subcontract agreement(s), should the need arise to verify that the subcontractor/supplier is performing a commercially useful function.
-
CONTRACT EXECUTION AND MONITORING PHASE
-
The MWBE Program Coordinator will, with the assistance of other campus staff, be responsible for monitoring compliance with the established MWBE goals during the life of the contract.
-
The campus will monitor and verify the contractor's compliance with Executive Law Article 15-A by discussing the following items during progress meetings:
-
any and all MWBE issues
-
any and all EEO issues
-
copies of meeting minutes and e-mail communications
-
MBE utilization
-
WBE utilization
-
EEO utilization.
-
The MWBE Program Coordinator will require the contractor to report their MWBE Contractor Compliance & Payments directly online by logging into the New York State Contract System (NYSCS) https://ny.newnycontracts.com/ and responding to the monthly Compliance Audit Reminder.
-
Monthly Compliance Audit Reminders will be sent automatically during reporting periods which payments have been made to the prime.
-
Contractors that are required to report should do so upon receipt of the NYSCS Audit Reminder over the term of the contract documenting the progress made toward achievement of the MWBE goals of the Contract.
-
The MWBE Program Coordinator will require the contractor to submit the Workforce Utilization Report directly online by logging into the NYSCS https://ny.newnycontracts.com/ and responding to Workforce Audit Reminders, and to require any of their subcontractors on the contract to do the same, on a monthly basis for construction contracts, and a quarterly basis for all other contracts, during the term of the contract.
-
In accordance with 5 NYCRR § 141.4, the MWBE Program Coordinator is required to review the aforementioned submitted audits to ensure the following:
-
If payments have been made to the Prime
-
If payments have been made to the Sub contractor(s)
-
Is the contract on track to meet the established goals during the life of the contract
-
SUNY's compliance process will be outlined in a training documents to assist campus staff in developing an internal controls to ensure contractor adherence to NYS Executive Law Article 15-A.
-
If requested, the Business Officer or campus designee, shall require the contractor to provide access to other relevant documentation (e.g., books, records, and payroll records) relating to their operations and implementation of their affirmative action or equal employment opportunity program in effect as of the date the contract is executed.
-
Any waivers of compliance issued by the System-wide MWBE Program, or modifications to the utilization plan, shall be posted on the System-wide MWBE Program website, or a campus website, if they have the capacity, within ten (10) business days of making such a decision.
-
Within one hundred twenty (120) business days after completion of a contract, the MWBE Program Coordinator close out the contract in the NYSCS.
-
DOCUMENTATION OF GOOD FAITH EFFORTS - The University's Responsibility
-
The MWBE Program Coordinator should be pro-active in their outreach and make it easier for MWBEs to participate directly and/or partner with Prime contractors by:
-
Directly notifying MWBEs of open eligible procurements posted to Contract Reporter
-
Directly inviting MWBEs to participate as Prime or Sub contractors
-
Providing Prime contractors with lists of MWBEs who may be able to subcontract
-
The campus is responsible for verifying documentation provided by the vendor to demonstrate good faith efforts to obtain MWBE participation in State contracts to facilitate compliance with this obligation. The MWBE Program Coordinator in coordination with other campus staff should include relevant documents as described below in the procurement record:
-
Approved MWBE forms:
-
MWBE Utilization Plan approved in the NYSCS
-
MWBE-EEO Staffing Plan (7557-108)
-
Other relevant documentation as outlined in Section VI
-
Approved waiver notification (email) from the System-wide MWBE Program
-
DISCRETIONARY BUYING AUTHORITY
-
NYS Finance Law 163.6 (b) - Discretionary Buying Threshold for the MWBE Program
As stated in Item 7553 (Purchasing and Contracting), and consistent with NYS State Finance Law Section 163.6, where commodities or services are available from New York State certified MWBEs, purchases may be made by the University in amounts not exceeding $500,000 without competitive bidding.
-
The discretionary threshold of up to $500,000 for procurements from small, minority- and women-owned business does NOT apply to construction & construction-related consultant services.
-
The campuses are required to document in the procurement record support for both the reasonableness of the price and the selection of the vendor.
-
Advertising requirements under NYS Economic Development Law still apply. The appropriate language when advertising in the NYS Contract Report is provided below:
“SUNY intends to procure (insert project description, i.e. 1,000 widgets) pursuant to its discretionary purchasing authority under State Finance Law section 163(6). This procurement opportunity is limited to New York State businesses certified pursuant to Article 15-A of the New York State Executive Law.”
Please note: NYS Finance Law 163 6-b stipulates that the reasonably expected aggregate amount of all purchases of the same commodities or services from the same provider within the twelve-month period commencing on the date of the first purchase cannot be an amount greater than the discretionary buying threshold amount for that agency. Additionally, purchases of services or commodities shall not be artificially divided for the purpose of satisfying the discretionary buying thresholds. Finally, unbundling (5 NYCRR Part 141.5(c) (2)) is recognized as a best practice when utilizing this provision of the SFL.
-
Elements of Good Faith Effort for Discretionary Procurements (not exceeding $500,000):
(See SUNY Policy Item 7553 [Purchasing and Contracting] for an explanation of discretionary procurements under $50,000 and between $50,000.01 and $500,000)
-
Justification for the selection of vendor may be supported by:
-
demonstrating reasonableness of price
-
showing enhanced or additional value provided by the vendor
-
noting the vendor is a NYS small business(if applicable)
-
identifying the vendor is an MBE or WBE (this cannot be the sole justification)
When an MWBE submits a quote for a commodity or service for a discretionary procurement (not exceeding $500,000) and the quote is deemed high, the campus is encouraged to engage in direct negotiation with the MWBE firm in an attempt to reach reasonableness of price. This good faith effort is not applicable for a formal competitive procurement (i.e., sealed bid) as defined in SUNY Procedure Item 7553.
-
Reasonableness of Price (methods of establishing) - including, but not limited to:
-
comparing the quoted price with the price for the same or similar services within the last six months;
-
comparing the price with other quoted prices;
-
comparing the quoted price with prices in various procurement publications;
-
reviewing the type of work that was previously accepted by the campus at a similar price; and
-
comparing the quoted price with cost to other governmental entities.
-
Follow-up telephone calls to MWBE vendors are encouraged (e.g., to determine if the vendor plans on submitting a quote or to engage in negotiations).
Definitions
Bid - binding price offering that has been submitted in a sealed envelope to prevent dissemination of its contents before the deadline for the submission of all bids.
Equal employment opportunities (EEO) - The conscientious and active efforts by a contractor to afford employment opportunities to minority group members and women without discrimination because of race, creed, color, national origin, sex, age, disability or marital status.
Goals - The term referring to the percentage of aggregate agency expenditures targeted for the participation of certified minority- and/or women-owned business enterprises sought to be included in State procurement opportunities as prime contractors, subcontractors, suppliers, consultants, joint ventures, teaming agreements, or other similar arrangements. Goals may be expressed as annual Statewide (also referred to as "Section 313 goals"), agency-specific, or contract goals.
Joint venture - A contractual agreement joining together two or more business enterprises, one of which is a certified minority - or women-owned business enterprise, for the purpose of performing on a State contract. The certified minority- or women-owned business enterprise must provide a percentage of value added services representing an equitable interest in the joint venture. All parties agree to share in the profits and losses of the business endeavor according to their percentage of equitable interest.
Mentor-Protégé Agreement - A contract between a prime contractor, the "Mentor," and a minority- or women-owned business enterprise, the "Protégé," in which there is a transfer of knowledge, technology, or other resources, which promotes the economic growth of the minority- or women-owned business enterprise or fosters the establishment of a long term business relationship between the parties.
Minority group member - A United States citizen or permanent resident alien who is and can demonstrate membership in one of the following groups:(a) Black persons having origins in any of the Black African racial groups;(b) Hispanic persons of Mexican, Puerto Rican, Dominican, Cuban, Central or South American of either Indian or Hispanic origin, regardless of race;(c) Native American or Alaskan native persons having origins in any of the original peoples of North America;(d) Asian and Pacific Islander persons having origins in any of the Far East countries, South East Asia, the Indian subcontinent or the Pacific Islands.
Minority-owned business enterprise - A business enterprise, including a sole proprietorship, partnership or corporation which has been certified as minority-owned by the Empire State Development's Division of Minority and Women-Owned Business Development.
Quote - non-binding statement of price, terms of sale, and description of goods or services offered by a vendor as a basis for negotiations for entering into a contract.
State Contract - (a) a written agreement or purchase order instrument, providing for a total expenditure in excess of twenty-five thousand dollars ($25,000.00), whereby the State University of New York ("University") is committed to expend or does expend funds in return for labor, services including but not limited to legal, financial and other professional services, supplies, equipment, materials or an combination of the foregoing, to be performed for, or rendered or furnished to the University; (b) a written agreement in excess of one hundred thousand dollars ($100,000.00) whereby the University is committed to expend or does expend funds for the acquisition, construction, demolition, replacement, major repair or renovation of real property and improvements thereon; and (c) a written agreement in excess of one hundred thousand dollars ($100,000.00) whereby the University as an owner of a state assisted housing project is committed to expend or does expend funds for the acquisition, construction, demolition, replacement, major repair or renovation of real property and improvements thereon for such project.
Subcontract - Any agreement for a total expenditure in excess of $25,000 providing for services, including non-staffing expenditures, supplies or materials of any kind between a State agency and a prime contractor, in which a portion of the prime contractor's obligation under the State contract is undertaken or assumed by a business enterprise not controlled by the prime contractor.
Teaming Agreement - A utilization plan arrangement between two or more parties, one of which is a certified minority- or women-owned business enterprise, to perform on a specific State contract if awarded to the team. The team itself may be a joint venture, or one of the team members may be designated to act as the prime contractor, and the other member(s) designated to act as subcontractors.
Unbundling - a process whereby the procurement contract is divided into smaller parts to provide NYS certified MWBEs better access to SUNY's procurement opportunities. Unbundling can be divided into two types, horizontal and vertical. The horizontal unbundling divides the procurement contract into multiple lots. Vertical unbundling divides each lot into different phases of the procurement process. This offers opportunities for campuses to prepare a bid on one or a larger set of lots, where each of the phases offers new opportunity for MWBE participation. Procurement staff may reduce barriers to bid packages by employing the strategy of "unbundling" projects.
Utilization plan - The plan which must be submitted by a contractor to a State agency listing certified minority- and/or women-owned business enterprises that the contractor intends to use in the performance of a proposed State contract, or any components of the contract scope of work which the contractor intends certified minority- and/or women-owned business enterprises to perform. The plan shall specifically contain a list, including the name, address and telephone number of each certified enterprise with which the contractor intends to subcontract, or otherwise submit in connection with satisfaction of the contract goals.
Women-owned business enterprise - a business enterprise, including a sole proprietorship, partnership or corporation that has been certified as women-owned by the Empire State Development's Division of Minority and Women-Owned Business Development.
7557-101 - M/WBE Contractor Solicitation Letter
7557-102 - M/WBE Participation Quote
7557-103 - M/WBE Contractor Unavailability Certification
7557-104 - MWBE-EEO Policy Statement
7557-105 - M/WBE-EEO Work Plan
7557-106 - Contract Breakdown and Sample
7557-107 - MWBE Utilization Plan
7557-108 - EEO Staffing Plan
7557-111 - Monthly MWBE Compliance Report
7557-113 - Quarterly MWBE Compliance Report
7557-114 - Prime MWBE Post Solicitation Waiver Request
7557-114a - Campus MWBE Post Solicitation Waiver Request
7557-114b - Campus MWBE Pre Solicitation Waiver Request
7557-120 - Compliance Check List
7557-121a - Prospective Bidders Notice Commodities Services
7557-121b - Prospective Bidder's Notice Construction
7557-121c - Prospective Bidder's Notice Construction-Related Consultant Services
7557-122 - MWBE Program Coordinator Designation
7557-123 - Pre-bid Information Script
7557-124 - Good Faith Efforts - Criteria to Evaluate Quality of Design Firm Response (Construction
Consult Selection Process)
7555-15 - Sub-Consultant Staffing List - Architecture and Engineering
7555-16 - Sub-Consultant Staffing List - Construction Management
7555-17 - Sub-Consultant Staffing List - Commissioning
7557-125 - Diversity Practices Scoring Rubric Form
7557-126 - Diversity Practices Scoring Matrix Form
7557-110 - EEO Workforce Utilization Report
7557-109 - Campus Consultant/Contractor Affidavit
April 2024 – updates to clarify procedure
August 2021 – updates to clarify the required documentation for EEO on construction contracts.
On January 25, 2012 the State University of New York Board of Trustee adopted a resolution on Minority- and Women-owned Business Enterprise (MWBEs) Utilization Reports.
New Rules and Regulations were created and took effect on December 22, 2010, under 5 NYCRR Part 140. On July 15, 2010 New York State passed the Business Diversification Act, amending Article 15-A.
On April 29, 2010 the New York State Disparity Study was released by Department of Economic Development Article 15-A of the Executive Law, signed into law on July 19, 1988, authorized the creation of an Office (now Division) of Minority and Women's Business Development to promote employment and business opportunities on state contracts for minorities and women.
Memorandum to Presidents 84-3 dated April 6, 1984, Amendment to Policy on Minority Business Enterprises. On August 3, 1983, Governor Cuomo issued Executive Order 21 that superseded Executive Order 117 and included women-owned business enterprises.
Memorandum to Presidents 83-8 dated July 1, 1983, Policy on Minority Business Enterprises. On December 9, 1981, Governor Carey issued Executive Order 117 related to minority-owned business enterprises.